Newtown Creek Wastewater Treatment Plant

Location

Years

1999 -2019

New York

Owner

NYCDEP

Contract Amount

$5,000,000,000

Service

Wastewater

CSM has served as a subconsultant to the Hazen and Sawyer, Malcolm Pirnie and Greeley and Hansen JV team for the past 20 years. As this project has had an ever-changing list of needs, CSM has been called upon to provide staff in the following roles: Resident Engineer, Office Engineer, Electrical Engineer/ Inspector, Mechanical Engineer/Inspector, Cost Estimators, and Civil Inspectors. We have had approximately 26 staff members on this job. The project scope included demolition of existing structures, construction of new building facilities, grit chambers and settlement tanks. CSM’s staff participated in the following contracts:

Contract No. 27 Construction of the C.M. Building

Contract No. 29 Reconstruction of multiple roads of Kingsland Avenue including new storm and sanitary sewers with house reconnections, water mains with hydrants and hydrant branches, and new water services

Contract No. 31 Sludge handling facilities; 8 digesters and 24 new centrifuges Contract No. 35G and 35E North Battery of Aeration and Final Tanks

Previous
Previous

BPCA - Battery Park Resiliency Project

Next
Next

Croton Reservoir Water Treatment Plant