Ed Koch Queensboro Bridge

Years
2019-2022
Location
NYC
Contract Amount
$315,000,000
CSM Services
Bridges
Owner
NYCDOT

PROJECT BRIEF

CSM is providing third-party review of the demolition procedures being proposed by the Contractor, Skanska, as part of the rehabilitation of the Ed Koch Queensboro Bridge under Contract 10.

This project includes an upper deck replacement on the main bridge, upper deck rehabilitation on both approaches, structural steel rehabilitation, deck joints and barrier replacement, lighting and drainage improvements, incidental bridge painting, and fire standpipe system replacement.